Carbonology Starts Installation of Its First Unit at the Ningdong Pilot
Pilot Project Construction Update
October 2026 · Ningxia
Carbonology's 1,000-tonne DAC-to-SAF pilot project has moved from the main structural construction phase into equipment installation, with overall project progress nearing 70%.
Building on completed foundation works, including excavation and lime-soil replacement, large on-site machinery such as tower cranes and concrete pumps is now in place, while structural works for multiple building units are progressing in parallel. Two key utility units—the fire water pump house and 10kV substation—have topped out, laying the groundwork for the delivery and installation of high-power process equipment. The administration complex and central control building have also reached structural topping, and secondary structural works are now underway. As the control nerve centre of the entire facility, the central control building's timely completion will support the subsequent installation and commissioning of the control system.

Breakthroughs have also been achieved in the core process area: foundations and short columns for the CO₂ capture unit have been poured, and lifting operations for the framework of the first direct air capture (DAC) unit began this week. Work on the utility station and pipe racks PR5/PR6 is advancing on schedule. Construction of the temporary solid and hazardous waste storage room is nearing completion, with supporting functions being finalised.

Looking ahead to the second half of October, the project will enter a phase of overlapping civil works and equipment installation. Civil works will continue on the Class A tank farms, pipe racks, and site-wide supporting facilities; installation of the core DAC capture unit will be completed; and installation of process, electrical, and utility equipment will commence in tandem. The project targets substantial completion of the main works by December 2026, followed by equipment commissioning and integrated system testing to pave the way for Phase 1 commissioning and operation.

Positioned as an engineering-scale pilot validation platform, Carbonology's 1,000-tonne DAC-to-SAF pilot project integrates the complete process chain of direct air carbon capture, CO₂ reduction, and advanced Fischer–Tropsch synthesis. It will validate engineering scale-up and generate real-world operational data to underpin commercial deployment.